01Requirement
What the site needed
The infrastructure program moved along the route every 18 months, and the office had to stay usable through winter with minimal site work.
A project office compound with meeting rooms, canteen and welfare, relocated between construction phases.
02Configuration
Unit list
Reference quantities. Final scope follows the approved project schedule.
| Unit | Qty | Note |
|---|---|---|
| Office module | 14 | Open plan and project rooms |
| Meeting module | 4 | 8 – 16 seats |
| Canteen and welfare | 6 | Kitchen, WCs and drying room |
03Delivery
Delivery notes
01
Ground screws
No concrete, so the compound can be removed cleanly.
02
Covered links
Canopies connect modules for winter circulation.
03
Relocation
Modules labelled and craned to the next compound in one move.
04Site gallery