Data CentersScene reference
Containerised power module assembly
- Location
- Factory, China
- Business line
- Data Centers
- Application
- Power modules
- Delivery form
- 40ft power containers
01Requirement
What the site needed
Each batch had to leave the factory with protection settings, fuel systems and cable entries already witnessed and sealed.
White 40ft enclosures fitted with generator sets, fuel tanks, controls and cable interfaces before dispatch.
02Configuration
Unit list
Reference quantities. Final scope follows the approved project schedule.
| Unit | Qty | Note |
|---|---|---|
| Enclosure | 40ft | Insulated, louvred and fire-rated |
| Generator set | 1 per unit | Bulk fuel tank and exhaust |
| Control panel | 1 per unit | ACB, metering and changeover |
03Delivery
Delivery notes
01
Factory fit-out
Mechanical, electrical and fuel systems installed on one line.
02
Witness test
Load bank, protection and interlock checks before packing.
03
Dispatch package
Lifting points, transport frames and connection drawings included.
04Site gallery
Images
Discuss a similar project