Data CentersScene reference
Edge site power upgrade, Chile
- Location
- Antofagasta, Chile
- Business line
- Data Centers
- Application
- Power and UPS expansion
- Delivery form
- 3 power cabins
01Requirement
What the site needed
The existing node ran on a single feed with limited ride-through, and the upgrade had to be connected without interrupting live racks.
Transformer, LV distribution and UPS cabins added to an operating edge node.
02Configuration
Unit list
Reference quantities. Final scope follows the approved project schedule.
| Unit | Qty | Note |
|---|---|---|
| Transformer cabin | 1 | Dry-type, LV compartment |
| UPS and battery cabin | 1 | Modular UPS, lithium racks |
| Distribution cabin | 1 | Outgoing feeders to compute |
03Delivery
Delivery notes
01
Live tie-in plan
Temporary feed and switching sequence agreed with operations.
02
Cabin testing
Factory witness test of protection and changeover.
03
Cutover window
Migration completed inside a planned maintenance window.
04Site gallery
Images